Coorparoo State School 25m pool

Ozcrete sub contracted to Qbuild for the construction of the new 25m wet deck swimming pool. This covered surveying and set out of the pool, site management, removal and stockpiling the top soil from the oval, construction of a gravel road way to carry the trade vehicles and trucks during construction, excavation, underground storm water plumbing, including pit and head wall, formwork, steel fixing, concrete spraying of pool shell, and balance tanks & placement of concrete for all the concrete concourse and surrounding concrete areas, tiling pool water line tiles, wet deck tiles and grates, supply and fit ladders and lane rope holders, construction of concrete starting blocks, supply and installation of the all pipe work to the filter, landscaping, construction of a core filled retainer wall, relocation of existing shade structure and earth bonding. This project was started on the 7/1/2003 and finished on the 9/5/2003.

Category

New Pool

Client

Qbuild

Completed

05/2003